Vertical construction of the Oak Street Parking Garage has been completed, according to the project’s general contractor. The project brings more than 400 new parking spaces to the downtown area. Based on the final, revised, and accepted project schedule, all construction will be completed by March 31 as long as there are no significant weather delays.
See an updated map of downtown parking.
Placer County Transportation Planning Agency (PCTPA) is working with several agencies to to reconfigure the Highway 65 interchange at Interstate 80.
Phase I, which has been funded, will add a third lane on northbound Highway 65 from Interstate 80 to Pleasant Grove Boulevard.
While Phase 1 is moving forward this year, the time to complete the overall project may take 20 years or more depending on available funding.
Read more here.
Big Spoon Yogurt
Big Spoon Yogurt, located at The Fountains, is under new ownership! Create your own frozen yogurt treat by choosing from more than 75 delicious toppings!
FlexCare is remodeling their offices at 532 Gibson Drive, S-250. The improvements are valued at nearly $100,000 for approximately 6500 square feet of leased space. FlexCare is a Joint Commission-certified provider for healthcare staffing services throughout the U.S.
First Foundation Bank
First Foundation Bank is remodeling offices at 2233 Douglas Blvd., Suite 300, valued at over $50,000.
|
|
|
Placer Food Bank is remodeling space at their current 8284 Industrial Avenue, Suite 100 location, valued at nearly $50,000. Placer Food Bank provides hunger relief to El Dorado, Nevada, and Placer Counties.
|
|
McDonald's Remodel
McDonald's has applied for permits to demolish and rebuild their restaurant at 120 Harding Blvd. The valuation of the work is approximately $500,000. The original structure was built in 1972.
|
Alta California Regional Center (ACRC) is processing tenant improvements for approximately 9,700 square feet of leased tenant space valued at $145,000. ACRC is a private, non-profit corporation working under contract with the State of California, Department of Developmental Services, to provide services to persons with a developmental disability pursuant to the Lanterman Act.
|
|
Sikh Temple
The Sikh Temple is processing plans to construct a 59,000 square foot temple at 1090 Main Ave. The project is valued at over $4 million.
|
|