SR 104 - Hood Canal Bridge - Center Lock Rehabilitation

SR 104 Hood Canal Bridge overnight closures have been cancelled for the rest of May. Closures resume Monday, June 3. See the "what to expect" section of this page for a full schedule.

Project overview

Crews will upgrade and replace key elements of the SR 104 Hood Canal Bridge. The construction bolsters systems that guide the bridge together and keep both halves of the bridge connected.

Timeline
May 2021 - June 2024
Project status
Construction
Funding
$1.28 million

What to expect

SR 104 Hood Canal Bridge will be closed 10 p.m. to 5 a.m. most nights between June 3 and June 14

Instead of long-term weekend closures of the bridge, WSDOT made the decision to separate the work into phases. This means the bridge will be closed overnight 10 p.m. to 5 a.m., mostly on weeknights. The bridge will be open to traffic Memorial Day weekend.

The bridge will close at 10 p.m. on each of the following dates. It will reopen at 5 a.m. each following morning.

  • Monday, June 3 through Saturday, June 8
  • Monday, June 10 through Friday, June 14

Closures require good weather and calm tides, so they may be rescheduled.

Daytime center lock work

In addition to the nighttime closures, crews will work during the day on the bridge's locking mechanism. The bridge will remain open to traffic during this work. It does require short 30 to 40-minute test openings during weekday daytime hours. This is about as long as a typical inspection opening.

These test openings are scheduled for some time between 7 a.m. to 5 p.m. May 24, May 28-29 and June 14.

Map of SR 104 Hood Canal Bridge repair project.