What is Happening?
- Construction of a 81,000 square foot hospital & clinic
Schedule
- Open Air Open House - September 18, 2022
- Core & Shell Drawing Set Release For Bidding – December 2022
- Enclosure & Interior Drawing Set Release For Bidding – March 2023
- Construction Start – March 2023
August 2022 Update
Work Completed
- Schematic Design Estimate
Work Ongoing
- Finalize Building Design
- Finalize Site Design
- Individual Room Layout Planning
- Finishes Planning
Work Upcoming
- Design Development Document Completion
- Design Development Estimate
Megan Geiser, Project Manager