Army Navy Drive Complete Street
Status
Construction
Construction of the Army Navy Drive Complete Streets project started in July 2023 and is anticipated to reach completion in late 2025.
Project Location
This project is located in the Pentagon City neighborhood, on Army Navy Drive, between South Joyce Street and 12th Street South.
Project Updates - Fall 2024
Phases 2A and 2B
Crews will be working on sidewalks, bike lane medians, curb and gutter, storm structures, signal and streetlight infrastructure, and other work as part of phases 2A and 2B. This work is expected to be completed in spring of 2025.
Lanes and sidewalks will close periodically adjacent to work sites to ensure worker and traveler safety.
Phase 2A Map
Phase 2B Map
Phase 3
Beginning in mid-November and extending through the end of the year, this phase of construction will complete the center medians proposed along the entire Army Navy Drive corridor from South Joyce Street to 12th Street South. Some segments will consist of striping only, and other segments will be a raised-curb design.
During this time, the left lanes in each direction will close periodically to accommodate work as crews move forward.
Phase 3 Map
Traffic Impacts During Construction
As of August 2024, the former eastbound righthand lane side of Army Navy Drive was permanently closed to construct the two-way cycle track. Additionally, many of the driveway entrances along the Army Navy Drive within the project area will be reconfigured for improved safety and efficient shared use by all travelers.
Construction will proceed from end to end of the project site within each phase of the project. During this time, travelers should expect lane and sidewalk closures, bus stop relocations, and slower traffic.
Pay attention to signs indicating closures and detours and proceed with caution to keep workers, other travelers, and yourself safe.
About the Project
The project will rebuild Army Navy Drive within the existing right-of-way as a multimodal complete street featuring enhanced bicycle, transit, and pedestrian facilities. The goal of the project is to improve the local connections between the Pentagon and the commercial, residential and retail destinations in Pentagon City and Crystal City.
Watch the project video
Phase 1 - Demolition of Medians and Roadway Pavement
Crews will demolish the medians on Army Navy Drive, starting at South Joyce Street to the west, and progress eastward to the project terminus at 12th Street South.
The demolished medians will be rebuilt in Phase 3.
Phase 2A & 2B - Sidewalks, Streetlights, Protected Bike Lanes
Phase 2A: Crews will work on the streetlights, drainage, and curb & gutter, along the sidewalks on Army Navy Drive in the project area. The plan is to work in a counterclockwise direction, starting at the southeast corner of Army Navy Drive & South Fern Street, proceeding eastward on the southern side of Army Navy Drive, then returning westward on the north side.
The traffic signal equipment at the five signalized intersections will be replaced with new equipment.
Phase 2B: The reconstruction will provide a physically separated two-way protected bicycle lane facility along the south side of Army Navy Drive, in addition to shorter and safer pedestrian crossings, and will accommodate future dedicated transit lanes.
Phase 3 - New Medians
Crews will install new striped medians as part of the reconfigured Army Navy Drive.
Phase 4 - Road Surface Work
The reconstructed Army Navy Drive will feature enhanced intersections to be safer for pedestrians and cyclists crossing the streets, and improved infrastructure for buses.
Phase 5 - Striping, Markings, Signage and Landscaping
New markings and signage will bring greater visibility to this comprehensive multimodal facility.
The project began working through a detailed traffic operations analysis in summer of 2015. This study evaluated the multimodal travel impact of the proposed improvements on the surrounding future 2020 and 2040 Pentagon City and Crystal City street network. The traffic analysis was approved by the Virginia Department of Transportation in December 2017. Based on the recommendations and results in the final analysis, the project’s working concept plan was updated to enhance the multimodal access and mobility of the Army Navy Drive project corridor.
Project Timeline:
- Final design submission – Fall 2021
- Bid/Contract document preparation – Fall 2021
- Bid advertisement – Winter 2021-22
- Completion of easement acquisitions – Winter 2021-22
- Construction start - Spring/Summer 2023
- Anticipated construction completion - Late 2025
Connections to Other Projects
This project will extend the Crystal City Potomac Yard Transitway into Pentagon City by adding one dedicated transit lane in each direction along Army Navy Drive between South Joyce Street and South Hayes Street.
And the project will link to the future two-way bicycle lane facility planned for South Clark Street between 12th Street South and 15th Street South and the future South Eads Street protected bike lanes.
Public Process
The County engaged with the public at different phases of the planning process for the Army Navy Complete Street project. See archived documents and comments below.
October 2022 Groundbreaking Ceremony
On October of 2022, Arlington County officials, representatives from state and regional transportation agencies, and business organizations broke ground to mark the beginning of construction on the Army Navy Drive Complete Street project.
November 2020 Design Public Meeting
The County held a design public hearing on Nov. 18, 2020. The hearing was held as a virtual/online meeting via Microsoft Teams.
Public comment on the project was collected by phone, email, mail, and in-person by appointment.
June 2019 Open House
An open house was held on June 25, 2019, at the Aurora Hills Branch Library. The online feedback form closed on July 12, 2019.
January 2018 Design Work Shop
A public design workshop was held on Jan. 31, 2018, at the Aurora Hills Branch Library. A comment period was open from the time of the meeting through Feb. 16, 2018.January 2018 Design Workshop
Community Briefings
Staff introduced the project to the Arlington County Bicycle Advisory Committee in December 2017 and the Crystal City Business Improvement District in January 2018 to solicit feedback on the design.
In June 2019, staff presented the 30 percent design plan to the Bicycle Advisory Committee
Read the Presentation
Funding
Project funding includes local and federal sources, regional funds from the Northern Virginia Transportation Authority, and private developer contributions.