[Federal Register Volume 85, Number 117 (Wednesday, June 17, 2020)]
[Notices]
[Pages 36574-36575]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-13033]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3511-024]


Lower Saranac Hydro, LLC; Notice of Application Tendered for 
Filing With the Commission and Soliciting Additional Study Requests and 
Establishing Procedural Schedule for Relicensing and a Deadline for 
Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: 3511-024.
    c. Date filed: May 29, 2020.
    d. Applicant: Lower Saranac Hydro, LLC.
    e. Name of Project: Groveville Hydroelectric Project.
    f. Location: On Fishkill Creek, in the City of Beacon, Dutchess 
County, New York. The project does not occupy any federal land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Ms. Elise Anderson, Senior Environmental 
Permitting Specialist, Lower Saranac Hydro, LLC, Enel Green Power North 
America, Inc., 100 Brickstone Square, Suite 300, Andover, MA 01810; 
Phone: (978) 447-4408 or email at [email protected].
    i. FERC Contact: Jeremy Feinberg at (202) 502-6893 or 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: July 28, 2020.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at [email protected], (866) 208-3676 (toll free), or (202) 
502-8659 (TTY).
    m. The application is not ready for environmental analysis at this 
time.

[[Page 36575]]

    n. The existing Groveville Mills Hydroelectric Project consists of: 
(1) A 167-foot-long, 37-foot-high concrete gravity dam, with a 140-
foot-long spillway having a crest elevation of 172.4 feet National 
Geodetic Vertical Datum of 1929 (NGVD29) and topped with 3-foot-high 
wooden flashboards; (2) an impoundment with a gross storage capacity of 
approximately 43 acre-feet and a surface area of 5 acres at a normal 
pool elevation of 175.4 feet NGVD29; (3) an intake structure with two 
gates and a 27-foot-high, 34-foot-wide trashrack; (4) a 9-foot-
diameter, approximately 140-foot-long riveted steel underground 
penstock; (5) a powerhouse containing three fixed-output turbine-
generator units with a total rated capacity of 927 kilowatts; (6) a 4-
foot-high submerged stilling basin weir approximately 60 feet 
downstream of the dam spillway; (7) a 20-foot-wide, 90-foot-long 
tailrace; (8) a 20-foot-long underground generator lead connecting to a 
step-up transformer that connects to a 13.2-kilovolt, 40-foot-long 
underground transmission line that then connects to a 15-foot-long 
aerial transmission line before connecting to the regional grid; and 
(9) appurtenant facilities.
    The project operates in a modified run-of-river mode. The project 
had an average annual generation of 1,762.7 megawatt-hours between 2012 
and 2019.
    o. A copy of the application may be viewed on the Commission's 
website at http://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document (P-3511). For assistance, contact FERC 
Online Support at [email protected] or call toll-free, (866) 
208-3676 or (202) 502-8659 (TTY). At this time, the Commission has 
suspended access to its Public Reference Room due to the proclamation 
declaring a National Emergency concerning the Novel Coronavirus Disease 
(COVID-19) issued by the President on March 13, 2020.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate.

Issue Deficiency Letter (if necessary)--August 2020
Request Additional Information--August 2020
Issue Acceptance Letter--November 2020
Issue Scoping Document 1 for comments--December 2020
Request Additional Information (if necessary)--February 2021
Issue Scoping Document 2 (if necessary)--March 2021
Issue Notice of Ready for Environmental Analysis--March 2021
Commission issues Environmental Assessment (EA)--September 2021
Comments on EA--October 2021

    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

Kimberly D. Bose,
Secretary.
[FR Doc. 2020-13033 Filed 6-16-20; 8:45 am]