[Federal Register Volume 85, Number 14 (Wednesday, January 22, 2020)]
[Notices]
[Page 3667]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-00967]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP20-36-000]
Rover Pipeline LLC; Notice of Application
Take notice that on January 9, 2020, Rover Pipeline LLC (Rover),
1300 Main Street, Houston, Texas 77002, filed in the above referenced
docket an application pursuant to section 7(c) of the Natural Gas Act
(NGA) and Part 157 of the Commission's regulations for authorization to
increase the certificated mainline capacity on its pipeline system by
175 million cubic feet per day. Rover asserts that the proposed
increase in certificated capacity to 3.425 billion cubic feet per day
is supported by analysis of actual pipeline operating flow and pressure
conditions. Rover states that there will be no construction or
modifications to its existing facilities or services as part of this
proposal, all as more fully described in the application which is on
file with the Commission and open to public inspection. The filing is
available for review at the Commission in the Public Reference Room or
may be viewed on the Commission's website web at http://www.ferc.gov
using the ``eLibrary'' link. Enter the docket number excluding the last
three digits in the docket number field to access the document. For
assistance, contact FERC at [email protected] or call toll-
free, (866) 208-3676 or TTY, (202) 502-8659.
Any questions regarding this application should be directed to
Blair Lichtenwalter, Senior Director, Regulatory Affairs, Rover
Pipeline LLC, 1300 Main Street, Houston, Texas 77002, at (713) 989-
2605.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal Energy
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 3 copies of filings made in the proceeding with the Commission
and must provide a copy to the applicant and to every other party. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list and will be
notified of any meetings associated with the Commission's environmental
review process. Environmental commenters will not be required to serve
copies of filed documents on all other parties. However, the non-party
commenters will not receive copies of all documents filed by other
parties or issued by the Commission and will not have the right to seek
court review of the Commission's final order.
As of the February 27, 2018 date of the Commission's order in
Docket No. CP16-4-001, the Commission will apply its revised practice
concerning out-of-time motions to intervene in any new NGA section 3 or
section 7 proceeding.\1\ Persons desiring to become a party to a
certificate proceeding are to intervene in a timely manner. If seeking
to intervene out-of-time, the movant is required to ``show good cause
why the time limitation should be waived,'' and should provide
justification by reference to factors set forth in Rule 214(d)(1) of
the Commission's Rules and Regulations.\2\
---------------------------------------------------------------------------
\1\ Tennessee Gas Pipeline Company, L.L.C., 162 FERC 61,167 at
50 (2018).
\2\ 18 CFR 385.214(d)(1).
---------------------------------------------------------------------------
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the eFiling link at
http://www.ferc.gov. Persons unable to file electronically should
submit an original and 3 copies of the protest or intervention to the
Federal Energy regulatory Commission, 888 First Street NE, Washington,
DC 20426.
Comment Date: 5:00 p.m. Eastern Time on February 3, 2020.
Dated: January 13, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-00967 Filed 1-21-20; 8:45 am]
BILLING CODE 6717-01-P