[Federal Register Volume 85, Number 50 (Friday, March 13, 2020)]
[Notices]
[Pages 14676-14677]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-05154]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14799-002]


Notice of Application Accepted for Filing, Soliciting Motions To 
Intervene and Protests, Ready for Environmental Analysis, and 
Soliciting Comments, Terms and Conditions, Recommendations, and 
Prescriptions; Lock 13 Hydro Partners, LLC

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Major License.
    b. Project No.: P-14799-002.
    c. Date filed: July 1, 2019.
    d. Applicant: Lock 13 Hydro Partners, LLC.
    e. Name of Project: Evelyn Hydroelectric Project.
    f. Location: On the Kentucky River, in Lee and Estill Counties, 
Kentucky. The project would be located at the Commonwealth of 
Kentucky's existing Lock and Dam No. 13. No federal land would be 
occupied by the project works or located within the project boundary.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: David Brown Kinloch, Lock 13 Hydro Partners, 
LLC, 414 S Wenzel Street, Louisville, KY 40204; (502) 589-0975; email_
[email protected].
    i. FERC Contact: Sarah Salazar, (202) 502-6863 or 
[email protected].
    j. Deadline for filing motions to intervene and protests, comments, 
terms and conditions, recommendations, and prescriptions: 60 days from 
the issuance date of this notice; reply comments are due 105 days from 
the issuance date of this notice.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene and protests, comments, terms and conditions, 
recommendations, and prescriptions using the Commission's eFiling 
system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE, Washington, DC 20426. The first page of any filing should 
include docket number P-14799-002.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted for filing and is now ready 
for environmental analysis.
    l. The proposed Evelyn Project would be operated in a run-of-river 
mode and would consist of: (1) An existing estimated 223-acre 
impoundment at a pool elevation of 617.38 feet mean sea level (North 
American Vertical Datum of 1988); (2) an existing concrete dam with a 
246-foot-long, 34-foot-wide, and 38.2-foot-high spillway and a 148-
foot-long, 38.2-foot-high, and 52-foot-wide lock chamber; (3) a new 64-
foot-long by 52-foot-wide reinforced concrete powerhouse that would be 
submerged in the existing lock chamber, with five horizontal turbine 
generator units each rated at 560-kilowatts (kW), for a total installed 
capacity of 2.8 megawatts (MW); (4) a new 110-foot-long buried cable 
transmitting power from the submerged powerhouse to a new two story, 
30-foot-long by 20-foot-wide Control Building onshore which would house 
the project controls; (5) a new 600-foot-long, 12.47-kilovolt overhead 
transmission line that would connect to an existing Jackson Energy 
Cooperative line of the same voltage; and (6) appurtenant facilities. 
The estimated average annual generation would be 12,161 megawatt-hours.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's website at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Any qualified applicant desiring to file a competing application 
must submit to the Commission, on or before the specified intervention 
deadline date, a competing development application, or a notice of 
intent to file such an application. Submission of a timely notice of 
intent allows an interested person to file the competing development 
application no later than 120 days after the specified intervention 
deadline date. Applications for preliminary permits will not be 
accepted in response to this notice.
    A notice of intent must specify the exact name, business address, 
and telephone number of the prospective applicant, and must include an 
unequivocal statement of intent to submit a development application. A 
notice of intent must be served on the applicant(s) named in this 
public notice.
    Anyone may submit comments, a protest, or a motion to intervene in 
accordance with the requirements of Rules of Practice and Procedure, 18 
CFR 385.210, .211, and .214. In determining the appropriate action to 
take, the Commission will consider all protests or other comments 
filed, but only those who file a motion to intervene in accordance with 
the Commission's Rules may become a party to the

[[Page 14677]]

proceeding. Any comments, protests, or motions to intervene must be 
received on or before the specified comment date for the particular 
application.
    All filings must (1) bear in all capital letters the title PROTEST, 
MOTION TO INTERVENE, NOTICE OF INTENT TO FILE COMPETING APPLICATION, 
COMPETING APPLICATION, COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, TERMS 
AND CONDITIONS, or PRESCRIPTIONS; (2) set forth in the heading the name 
of the applicant and the project number of the application to which the 
filing responds; (3) furnish the name, address, and telephone number of 
the person protesting or intervening; and (4) otherwise comply with the 
requirements of 18 CFR 385.2001 through 385.2005. All comments, 
recommendations, terms and conditions or prescriptions must set forth 
their evidentiary basis and otherwise comply with the requirements of 
18 CFR 4.34(b). Agencies may obtain copies of the application directly 
from the applicant. A copy of any protest or motion to intervene must 
be served upon each representative of the applicant specified in the 
particular application. A copy of all other filings in reference to 
this application must be accompanied by proof of service on all persons 
listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    o. Procedural schedule: The application will be processed according 
to the following schedule. Revisions to the schedule will be made as 
appropriate.

Commission issues EA November 2020
Comments on EA December 2020

    Dated: March 9, 2020.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2020-05154 Filed 3-12-20; 8:45 am]
 BILLING CODE 6717-01-P