Parliamentary question - P-000225/2021Parliamentary question
P-000225/2021

EU power supply failure

Priority question for written answer  P-000225/2021
to the Council
Rule 138
Claudia Gamon (Renew), Morten Petersen (Renew)

On Friday 8 January 2021, a power supply failure that is suspected to have originated in Romania disrupted the Continental Europe Synchronous Area. Its frequency dropped to 48.75 Hz (target frequency 50Hz), which caused the South-East area to be separated from the rest of the grid. This disruption and a lack of operating reserves in France nearly caused a Europe-wide blackout. Luckily, the automatic activation of power stations throughout Europe and the automatic initiation of contracted load shedding in Italy (1000 MW) and France (1300 MW) kept the grid stable and prevented a blackout. This incident shows the fragility of the grid and the real possibility of a Europe-wide blackout, which we need to prevent.

Last updated: 20 January 2021