[Federal Register Volume 84, Number 218 (Tuesday, November 12, 2019)]
[Notices]
[Pages 61047-61048]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-24569]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2814-025]


Great Falls Hydroelectric Company; City of Paterson, New Jersey; 
Notice Extending Scoping Comment Period

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.

[[Page 61048]]

    b. Project No.: 2814-025.
    c. Date Filed: February 28, 2019.
    d. Applicants: Great Falls Hydroelectric Company and the City of 
Paterson, New Jersey, as co-licensees.
    e. Name of Project: Great Falls Hydroelectric Project.
    f. Location: On the Passaic River, near the City of Paterson, 
Passaic County, New Jersey. The project does not occupy federal land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Mr. Robert Gates, Senior Vice President of 
Operations, Eagle Creek Renewable Energy, 65 Madison Avenue, Suite 500, 
Morristown, NJ 07960; (973) 998-8400; [email protected] 
and/or Ben-David Seligman, 2nd Assistant Corp. Counsel, City of 
Paterson, 155 Market Street, Paterson, NJ; (973) 321-1366; email_
[email protected].
    i. FERC Contact: Christopher Millard at (202) 502-8256; or email at 
[email protected].
    j. Deadline for filing scoping comments: December 23, 2019.
    The Commission strongly encourages electronic filing. Please file 
scoping comments using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-2814-025.
    k. This application is not ready for environmental analysis at this 
time.
    l. The existing project works consist of: (1) The Society for the 
Establishment of Useful Manufactures dam, an overflow granite stone 
gravity structure about 315 feet long, with a maximum height of 15 feet 
and having a crest elevation of 114.6 feet mean sea level (msl); (2) a 
reservoir with a surface area of 202 acres and a storage capacity of 
1,415 acre-feet at elevation 114.6 feet msl; (3) a forebay inlet 
structure; (4) a headgate control structure containing three trashracks 
and three steel gates; (5) three penstocks, each 8.5 feet in diameter 
and approximately 55 feet long; (6) a powerhouse containing three 
turbine-generator units with a total rated capacity of 10.95 megawatts; 
(7) a 37-foot-long, 4.16-kilovolt (kV) underground transmission line 
connecting the powerhouse to a 4.16/26.4-kV step-up transformer which 
in turn is connected to a 26.4-kV transmission grid via an 
approximately 30-foot-long, 26.4-kV underground transmission line; (8) 
and appurtenant facilities.
    The Great Falls Project is operated in a run-of-river mode. For the 
period 2010 through 2018, the average annual generation at the Great 
Falls Project was 17,484 megawatt-hours.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's website at http://www.ferc.gov using the eLibrary link. 
Enter the docket number excluding the last three digits in the docket 
number field to access the document. For assistance, contact FERC 
Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Scoping Process
    The Commission staff intends to prepare an environmental assessment 
(EA) for the Great Falls Project in accordance with the National 
Environmental Policy Act. The EA will consider both site-specific and 
cumulative environmental impacts and reasonable alternatives to the 
proposed action.
    Scoping meetings were held on October 23 and 24, 2019, near the 
project site in Paterson, New Jersey to receive input on the scope of 
the EA. The meetings were noticed in the Federal Register; however, it 
has come to our attention that the meetings were not noticed in a local 
newspaper. Thus, we are extending the comment period to December 23, 
2019.
    Copies of the scoping document (SD1) outlining the subject areas to 
be addressed in the EA were distributed to the parties on the 
Commission's mailing list and the co-licensee's distribution list. 
Copies of SD1 may be viewed on the web at http://www.ferc.gov using the 
eLibrary link. Enter the docket number excluding the last three digits 
in the docket number field to access the document. For assistance, call 
1-866-208-3676 or for TTY, (202) 502-8659.

    Dated: November 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-24569 Filed 11-8-19; 8:45 am]
 BILLING CODE 6717-01-P